Securing Feasibility Approvals: Standardizing the Annexure 1 Application Sheet
To register a residential customer under the **PM Surya Ghar Yojna**, the very first technical step after portal registration is submitting the **Annexure 1 Application Form** (Technical Feasibility Report) to the local DISCOM office. This sheet defines the connection parameter compliance and secures the formal approval for system installation.
Important Guidelines for Annexure 1:
- Technical Accuracy: The proposed solar plant capacity must not exceed the sanctioned load of the connection (unless the load is officially enhanced first).
- transformer Capacity Margin: Local DISCOM rules usually restrict total solar connections on a single distribution transformer to 80% of its total rated capacity. The faster you submit a correct Annexure 1, the faster you secure your slot.
How to Auto-Fill Annexure 1:
- Navigate to Net Metering ? Annexure 1.
- Choose your active customer from the list.
- All details (sanctioned load, connection phase, address) are automatically mapped.
- The PDF generator outputs the standard government form format perfectly. Click download, sign it, and upload to the central/state portal.